Timeline
This timeline reflects current estimates and may adjust as the project progresses.
Facility History
1979-1980
Wastewater Treatment Facility was constructed2001
First sludge removal completed; new aerators were installed2008-2009
New chemical feed equipment, headworks screen, and grit equipment installed2015
New NPDES permit adds treatment requirements for total phosphorous, lead, and copperSeptember 2023
New NPDES permit issued with lower limits for total phosphorus, lead and copper; new metals and nutrients added plus PFAS monitoringNovember 2023
Sludge measurements and sampling in the three lagoons confirms significant sludge accumulation
Project Planning & Approval
2024-2025
Engineering evaluation and facility planningJanuary 16, 2026
Bond hearing presentationJanuary 31, 2026
Deliberative SessionMarch 10, 2026
Town vote on bond warrant
Looking Ahead
2026-2027
Sludge Management plan development and approval, permitting, bidding, and constructionDecember 2027 (anticipated)
Project completion and start of bond repayment2027 & Beyond
Alternative Treatment Process to be designed and bid before next NPDES permit is issued